Dáil allows data-centre register Bill to advance
The Dáil granted leave to introduce the Data Centre Transparency Bill 2026 on 18 November 2026, allowing Deputy Jennifer Whitmore's proposal for a public register of data centres to move to the next legislative step.
Deputy Jennifer Whitmore said: "That leave be granted to introduce a Bill entitled an Act to establish a public register of data centres, to require certain data centres to report information relating to electricity consumption and water consumption as per requirements under Article 12 of the Recast Energy Efficiency Directive (EU/2023/1791), to confer functions on the Sustainable Energy Authority of Ireland; and to provide for related matters."
The Ceann Comhairle asked if the Bill was being opposed, and Minister of State Mary Butler replied: "It is not opposed." The question on leave to introduce the Bill was then put and agreed to.
Whitmore then moved: "That the Bill be taken in Private Members' time." That question was also put and agreed to.
Houses of the Oireachtas
- Dáil Éireann debate – Data Centre Transparency Bill 2026: First Stage, 18 November 2026
Ireland hosts approximately 123 data centres, which is around ten times the EU per capita average.
What the Bill would require
The Bill would establish a public register of data centres and require certain data centres to report information on electricity consumption and water consumption in line with Article 12 of the recast Energy Efficiency Directive, EU/2023/1791.
It would confer functions on the Sustainable Energy Authority of Ireland in relation to that reporting, and provide for related matters. Whitmore said: "This is a simple Bill. It puts on the national Statue Book exactly what the EU requires us to do."
She told the Dáil that Article 12 requires large data centres to report information to a central European database and that member states must establish the mechanisms necessary to collect, verify and oversee that reporting. She added: "In other words, governments must ensure transparency actually happens."
Whitmore said the current arrangement relied on operators reporting directly to the European Commission. She said: "Reports in the media reveal the Government was reluctant to establish a national oversight framework, preferring to rely on operators reporting directly to the European Commission, but that is clearly not working."
Houses of the Oireachtas
- Dáil Éireann debate – Data Centre Transparency Bill 2026: First Stage, 18 November 2026
Ireland hosts approximately 123 data centres, which is around ten times the EU per capita average.
Why power use and low reporting matter
Whitmore said Ireland hosts approximately 123 data centres, which she described as around ten times the EU per capita average, and said their growth had been one of the largest drivers of increased electricity demand on the grid.
In 2015, data centres accounted for 5% of Ireland's metered electricity consumption, she said, rising to 23% by 2025. She said EirGrid projects the share could increase to 30% by 2030, figures she said raise serious concerns during a cost-of-living and cost-of-energy crisis.
She said basic information about the sector is difficult to access and that many figures are based on estimates rather than hard data. She said neither the public, policymakers nor, it would appear, Government has access to information on how much energy individual centres use, how much water they use or what their efficiency levels are.
Only 18 of the approximately 123 Irish data centres had submitted information to the European database, she said, a compliance rate of 15%. She said: "Unfortunately, we have one of the lowest reporting rates in the EU with only 18 of the approximately 123 Irish data centres having submitted information to the European database, a compliance rate of 15%."
Houses of the Oireachtas
- Dáil Éireann debate – Data Centre Transparency Bill 2026: First Stage, 18 November 2026
Ireland hosts approximately 123 data centres, which is around ten times the EU per capita average.
Who pays, and what happens next
Céim a bhfuil súil léi: D’fhéadfadh an méid seo athrú.
Whitmore argued the costs fall on households and businesses through infrastructure and electricity demand. She said: "The public is paying for data centres. It pays much of the infrastructure costs and pays for the increased electricity demand."
She added: "The public has a right to know the true cost of data centres for electricity prices, emissions and the economy in general." She said the European Commissioner for energy had made clear that relying on direct reporting to the Commission would not fulfil member states' obligations under the directive.
The Government did not oppose First Stage, allowing the Bill to proceed. No detailed Government position on the contents of the register was set out at this stage.
As a Private Members' Bill, Second Stage must under Standing Orders be taken in Private Members' time. That debate, when scheduled, will consider the principles of the Bill in detail.
Houses of the Oireachtas
- Dáil Éireann debate – Data Centre Transparency Bill 2026: First Stage, 18 November 2026
Ireland hosts approximately 123 data centres, which is around ten times the EU per capita average.
Conas a rinneadh an scéal seo: dréachtaíonn DáilDex nuacht go huathoibríoch ó thaifid oifigiúla agus ó thuairisciú náisiúnta, agus seiceálann sé gach foinse agus sliocht roimh fhoilsiú. Léigh ár modheolaíocht
Foinsí
1 foinse
Oifigiúil / Príomhúil
- Houses of the Oireachtas — Dáil Éireann debate – Data Centre Transparency Bill 2026: First Stage, 18 November 2026
“Ireland hosts approximately 123 data centres, which is around ten times the EU per capita average.”